1.Check before starting, power on, check the tape machine before starting, make sure there are no big problems, do 5s.
2.Turn on the heat. After electrification, a heat engine is required to operate. Then, the winding machine into a state of normal ventilation, the parts of the normal operation before the next step.
3.Set the parameters, according to the near processing requirements to find the corresponding material specifications model, set the corresponding parameters in the winding machine.
4.Debugging. Parameters are set, does not mean that you can directly produce. Must be debugged to ensure that the machine parameters and components of the operation of coordination, production of product quality in line with standards.
5.Small Batch production. If it is not before the production of the transformer model, the first small batch trial production, to ensure that there will be no major problems.
6.Formal production. If there is no small batch, then the large batch will be put into production. At the beginning, engineering and technical personnel must be on duty, to ensure good operation, to the operator!